Downtown DOVA final approval came on November 2, when the Rancho Cordova City Council voted 4-1 to approve the financial participation agreement and adopt the development agreement for the arena district. Councilmember Joe Little cast the lone no vote, according to the Folsom Times and the Onsite Observer. The vote settles the entitlement question, but not the one about money.

The city’s staff report put the city’s financial participation at about $185M over 35 years. Both outlets report the final agreement doesn’t actually cap it there. Here is what changed since the October 26 vote, and what’s still open.

What Changed Between October 26 and November 2

The Onsite Observer reports three amendments, requested by a Marriott representative and accepted by the developer, KozPure Development:

  • Hotel tax timing: KozPure’s share of hotel tax is held until the arena receives its certificate of occupancy. An earlier draft allowed payments once the arena was 80% complete.
  • Shutdown clause: If the arena closes, the city can suspend or end the entire deal, not just the arena’s piece. Before the change, KozPure could have kept collecting from its hotels and shops.
  • DOVA Zone: The current boundaries are locked in, and KozPure gets half the hotel tax from new hotels in the zone.

The Folsom Times adds that the arena counts as operating with at least 30 events a year, with allowances for renovations. Staff project more than 180. Per the Onsite Observer, the city can suspend assistance after 30 days’ written notice and a council hearing.

The $185M Is an Estimate, Not a Cap

The Folsom Times says the $185M is the city’s projected maximum, but the agreement sets no explicit overall dollar cap on tax-sharing payments. The Onsite Observer reports the staff report says the subsidy “will not exceed” $185M, while the agreement and resolution contain no such limit.

The pieces that do have caps, per both outlets:

  • Permit fees: up to $3.7M waived, adjusted annually for inflation.
  • Impact fees: up to $13.5M, covered by transfers from the General Fund rather than eliminated.
  • Police: up to $500,000 a year for up to 15 years, starting after 75,000 SF of qualifying commercial space is occupied.
  • Fire: about $471,000 a year for up to 15 years, starting after the 100th housing unit is occupied. By simple multiplication, police and fire together come to about $14.6M, in line with the roughly $15M in the staff report.

The uncapped part is tax sharing. The developers get half of the city’s basic 1% sales tax from district businesses, plus eligible hotel tax minus a 2.5% city fee. Cardroom tax sharing covers up to 20 tables, if a cardroom gets separate approval.

The Onsite Observer reports each tax-sharing period is 35 years and they can start at different times. Hotel tax sharing can begin up to 10 years after the agreement takes effect. The disclosure puts the end date at November 2, 2066.

The City’s Own Projection

The city projects about $79.4M in receipts over 35 years from land sales, retained sales tax, property taxes, and fees, according to both the Folsom Times and the Onsite Observer. The reports don’t say how that figure relates to the $185M, and they aren’t the same kind of number. One is what the city could pay out. The other is what it expects to take in.

Councilmember David Sander told the council, “if it’s not built, none of that revenue exists,” per the Onsite Observer. That’s the central argument for the deal: most of the money flows only after construction and operations begin. The central worry from Little and other critics is the General Fund exposure, including the $13.5M in impact fees.

One document discrepancy is worth noting. The draft ordinance on the October 26 agenda described the development agreement with a 10-year term, extendable to a maximum of 19 years. Coverage of the final approval describes a 45-year term. The two may govern different agreements, so check the executed documents before relying on either.

Land and Schedule

The city is selling about 12.6 acres, per the Folsom Times and the Onsite Observer. The October 26 staff report said about 12.5. DOVA Arena LLC pays about $300,000 in cash for the smaller parcel, and the city finances 80% of the price on the rest. The sale remains subject to closing conditions. Neither outlet reports an updated appraisal.

The development agreement takes effect December 2, according to the Onsite Observer. KozPure targets construction within about 90 days, around late January or early February 2027, per the Folsom Times. The agreement requires “commercially reasonable efforts” to finish the arena by November 30, 2027, per the Onsite Observer. The Folsom Times calls that ambitious and notes the earlier Q1 2028 target for professional indoor soccer.

Financing is still the open item. The Folsom Times says construction financing, land conditions, and building permits must still be secured, and later phases need separate decisions and investment.

Traffic and Jobs

The Onsite Observer reports a traffic study estimating a sold-out Friday event would add about 2,300 vehicle trips between 6 and 7 p.m. Two Sunrise Boulevard intersections, at Coloma Road and Zinfandel Drive, would fall below the city’s congestion standard unless signals are retimed for events.

CBS Sacramento reports projections of 70 full-time and 300 part-time permanent jobs, and nearly 5,000 hires during construction. Those are the project leader’s projections.

What the Final Approval Means for Commercial Real Estate

The entitlement risk is mostly gone, but the financing risk isn’t. An adopted development agreement and an approved tax-sharing deal make the project more likely than it was a month ago. Construction financing hasn’t been reported yet, and the city’s assistance depends on the arena operating.

The DOVA Zone matters for hotel owners. KozPure gets half the hotel tax from new hotels in the zone, and a Marriott representative pushed for changes to the hotel terms. Consider a hypothetical owner of a hotel parcel within the zone. That owner should read the executed agreement to see how the zone boundaries affect competing development.

The exposure is hard to size. Tax sharing only pays if the district generates the taxes, which limits the downside. Because it isn’t capped, the total depends on how well the district performs.

What This Means

For owners: Owners near Kilgore Road and Trade Center Drive should treat the arena as likely, with a late 2027 target that could slip. Plan for event-day traffic on Sunrise Boulevard before any benefit from new visitors. If you own land in the DOVA Zone, get the executed agreement and read the zone terms.

For buyers: Price what exists, not the full $1.2B district. The Folsom Times notes the approval doesn’t guarantee later phases get built. Ask whether construction financing has closed, and what happens to the land sale if conditions aren’t met.

For tenants: Event-driven retail, restaurant, and hospitality demand won’t arrive until the arena opens, and the target is late 2027 at the earliest. Don’t lock in long leases at premium rents until construction is underway.

Greg Diodati, CCIM has been advising commercial real estate investors and owners since 1982. Call (916) 538-3399.

About Greg Diodati, CCIM

Greg Diodati, CCIM is a commercial real estate broker with RE/MAX Gold Commercial, serving Sacramento Metro. Since 1982, he has advised commercial property owners, investors, landlords, tenants, buyers, and business owners, with particular focus on commercial investment real estate and industrial properties.

Learn more about Greg Diodati, CCIM

STAY IN THE LOOP

Subscribe to our newsletter.

Leave A Comment