The Airport South industrial park is the biggest new supply story in Sacramento. Connect CRE reported on August 28 that NorthPoint Development has started design, engineering, and permitting for infrastructure on a roughly 4.7M SF park, with infrastructure construction planned to begin by 2028. That’s a long runway, and the timeline matters as much as the square footage.
Here’s what’s actually been approved, what’s still being fought, and what it means for owners of existing buildings.
What Airport South Is
The site sits in North Natomas, south of Metro Air Parkway and west of the Westlake neighborhood, according to CapRadio’s November 2025 coverage. CapRadio described about 450 acres across roughly 25 parcels, with four major warehouses plus a hotel, fast-food restaurants, and small utility buildings.
The land was protected through the Natomas Basin Conservancy in 1997, per CapRadio. The applicant says the site sits next to an existing logistics hub and fits the conservation plan.
The applicant claimed about 5,000 warehouse jobs, 3,800 construction jobs, and a $784M annual economic impact, as CapRadio reported. Those are NorthPoint’s projections, not independent findings.
Colliers holds the leasing assignment on the first four buildings, which total nearly 4M SF, per Connect CRE. NorthPoint is weighing build-to-suit projects, speculative buildings, and land sales to owner-users.
It’s Approved, but Not Settled
CBS Sacramento reported on January 6, 2026 that environmental groups, including the Environmental Council of Sacramento (ECOS), sued the City of Sacramento. The suits allege the City Council unlawfully approved the environmental impact report in December 2025.
CapRadio reported that the EIR lists unavoidable impacts, including a conflict with the region’s air quality plan. Natomas Unified officials also said a proposed 150-foot buffer to Paso Verde School was too small.
ECOS, an opposition group, reports that the developer agreed to some changes, including a larger setback. The sources reviewed report no court ruling on the suits. Anyone planning around Airport South should treat litigation as an open risk until the courts say otherwise.
How Big 4.7M SF Is in Sacramento
Kidder Mathews’ Q3 2026 Sacramento Industrial Market Report shows about 1.6M SF under construction across the whole market. Airport South at 4.7M SF is nearly three times that.
It’s also about 2.5 times the 1.9M SF North Market portfolio that Kidder Mathews lists as Q3’s largest industrial sale. And at roughly 2.5% of the 187.7M SF inventory Kidder Mathews tracks, it would be a meaningful addition to a market with 10.1% availability and a 6.1% direct vacancy rate.
Leasing is the other yardstick. Kidder Mathews counts 5,990,522 SF leased year to date through Q3. The nearly 4M SF Colliers is marketing equals about two-thirds of that, so this is a multi-year absorption job.
Why Existing Big-Box Owners Aren’t Doomed
Colliers’ Michael Hoo told Connect CRE that “there are very few remaining opportunities to develop large-scale distribution facilities.” Keep in mind Colliers is the project’s leasing broker, so that’s a marketing line. But it points at a real feature of the market: land for large buildings with entitlements is scarce, and Airport South has been through public hearings since at least 2025.
That scarcity cuts two ways. A new competitor is coming, and it also shows how hard it is to replace an existing big building. Existing, entitled, built space keeps its value for exactly that reason.
Airport South also targets large users. It won’t compete directly with a 20,000 SF small-bay building in Power Inn. The pressure lands on big-box product in Natomas and nearby submarkets.
The Timeline Is the Real Story
Infrastructure by 2028 means no buildings in 2026 or 2027. Add vertical construction, and deliveries come well after that. If NorthPoint pursues build-to-suit deals, the first buildings could be tied to specific users. If it builds speculatively, it will deliver into whatever the market looks like then.
Consider a hypothetical owner of a 500,000 SF building in the Natomas area with a lease expiring in 2029. That owner may face a tenant weighing a new-construction alternative. The owner’s best defense is to renew early, while the alternative is still a plan rather than a building.
The earlier piece on this site about Sacramento’s thin construction pipeline still holds for now. Airport South is the reason that may change at the end of the decade.
What This Means
For owners: Big-box owners in Natomas should start renewal conversations with tenants early, especially for leases expiring near the time Airport South could deliver. Small-bay owners aren’t directly exposed. If you’re considering a sale, the Q3 trades show buyers are active now, before this supply arrives.
For buyers: Underwrite large-format Natomas product with Airport South in the exit assumptions, not just today’s 10.1% availability. The lawsuits could delay or change the project. Don’t assume either outcome.
For tenants: Large users will have a new-construction option in the Sacramento area, possibly with build-to-suit terms. That gives you leverage in renewals today, but only if you can show you’d move. Watch the lawsuits and the 2028 infrastructure start before betting on a delivery date.
Greg Diodati, CCIM has been advising commercial real estate investors and owners since 1982. Call (916) 538-3399.
About Greg Diodati, CCIM
Greg Diodati, CCIM is a commercial real estate broker with RE/MAX Gold Commercial, serving Sacramento Metro. Since 1982, he has advised commercial property owners, investors, landlords, tenants, buyers, and business owners, with particular focus on commercial investment real estate and industrial properties.